School cleaning hours calculator
Explore your cleaning-hours assumptions
Indicative planning estimate
labour hours per cleaning day
Starting example: 1,000 m², five days, 39 routine weeks, 50 m²/hour and 100 deep clean hours.
Discuss this estimateAllow separately for supervision, setup and travel unless these are already included in your rate. This is a starting estimate, not a quotation or staff rota.
A transparent method for the first estimate
Daily labour hours = cleanable area ÷ assumed productivity. Weekly hours are daily hours multiplied by cleaning days. Annual routine hours are weekly hours multiplied by routine working weeks. Add periodic-cleaning hours only where they have been planned separately.
Use net cleanable area rather than the whole site or building footprint. The result is labour time, not the duration of a shift or a recommended number of staff.
The default 50 m²/hour is an illustration. It is an editable planning assumption, not a measured site rate, professional standard or guaranteed output. The site survey must establish an achievable rate for the actual tasks.
What changes the hours your school needs?
| Factor | Effect on the specification |
|---|---|
| Room use and furniture | Crowded teaching areas and detailed tasks need different allowances from open floors. |
| Toilets and personal care | Fixture-level tasks and equipment separation are poorly represented by area alone. |
| Floor type and condition | The right equipment, method and frequency affect the time required. |
| Access and circulation | Locked rooms, stairs, long travel routes and occupied spaces affect the sequence. |
| Setup and supervision | Show these allowances explicitly unless already built into the productivity assumption. |
| Periodic requirements | Price and schedule separately where not part of the routine programme. |
Turn the estimate into a room-by-room specification
List each room or zone, its cleanable area, surfaces, task frequencies and access window. Break out fixed-time tasks that do not scale with floor area, then check the total against a practical staff rota.
Validate the plan during mobilisation and use attendance and quality records to identify where the agreed tasks need a different method or allowance.
Download the survey checklistCalculator questions
Is the result a quote?
It is an indicative labour-hours estimate. It does not include a labour price, employer costs, equipment costs or a complete assessment of your school.
Should holiday weeks be entered as working weeks?
Only enter weeks using the routine daily schedule. Where holidays involve a different deep-cleaning programme, put the separately estimated labour hours in the periodic field.
Does a faster productivity rate always mean a better service?
No. A faster rate reduces calculated hours, but it needs to be achievable with the required tasks, equipment and standard. Test the assumption rather than treating speed as quality.