Check the current position before giving notice
Read the signed agreement for the term, renewal provisions, notice method and service-failure process. Record the issue you are trying to solve: staffing, standards, communication, scope or price.
Where the contract position is disputed, obtain advice before assuming a new contractor can start immediately. Follow the procurement rules applicable to your school or trust.
Build a useful tender or quotation brief
- Current room schedule, cleanable areas and actual access times.
- Required tasks, frequencies, routine weeks and periodic work.
- Relevant staffing and potential TUPE information, shared securely.
- Safeguarding requirements and site-specific risks.
- Reporting, audit, cover and escalation expectations.
- A consistent pricing schedule and treatment of exclusions.
Evaluate evidence as well as price
| Criterion | Evidence to request |
|---|---|
| Delivery plan | A workable rota, zone plan and explanation of proposed labour hours. |
| School suitability | Relevant experience supported by permissioned references or genuine case evidence. |
| Safeguarding and training | Site induction, appropriate checks and arrangements for relief staff. |
| Quality control | An example audit and a clear correction and escalation process. |
| Resilience | How absence, equipment failure and uncovered hours are handled. |
| Commercial clarity | Inclusions, exclusions, review terms and mobilisation responsibilities. |
Work backwards from a realistic start date
| Stage | Purpose |
|---|---|
| Before inviting prices | Review the current contract, procurement route and required service. |
| Quotation or tender period | Issue the specification, arrange surveys and clarify staffing assumptions. |
| Before appointment | Compare proposals, confirm the handover date and resolve material exclusions. |
| Before service transfer | Complete applicable employee processes, site inductions and access arrangements. |
| Opening weeks | Check attendance, inspect the agreed tasks and resolve handover issues. |
These are planning stages, not statutory procurement deadlines. The TUPE and mobilisation guide explains the employee-information step separately.
Contractor-change questions
Can the existing cleaners stay at the school?
A change of provider can involve a TUPE transfer, depending on the facts. Staffing should be assessed before the contract is priced or the start date is fixed.
How should we deal with historic cleaning complaints?
Keep dated records, follow the existing reporting process and identify the measurable service change you need. A new specification should make those expectations clear.